Sallins Road Roundabout Upgrade

Sallns Rd roundaboutWork on the Sallins Road roundabout has now started. I flagged this up when it was planned last year (see comments below). The work will involve making all the approaches to the roundabout two lanes and it will increase the flow through the roundabout helping to relieve congestion on the Monread and Sallins roads. I have discussed the traffic management plan with the District Engineer and whilst there may be some minor disruptions, the plan is to keep the roundabout open at all times throughout the work. The works will run on for a number of weeks, and probably last into the Autumn or later.

2 Replies to “Sallins Road Roundabout Upgrade”

  1. paul

    Just rang Kildare County Council Roads, and they said works due to complete by end December (which was also the plan)

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.